Completion of the project in due time at the predefined quality and cost is of the most important concern. Along with the increase of duration of project implementation, the total cost of the project will be raised due to annual inflation and other introduced costs. This research has investigated and identifies the most important causes of damage occurrences and time delay, then prioritized them throughout the project cycle from the pre-construction phase up to the end of the commissioning phase. Besides, solutions to prevent these damages and resolving the challenges ahead have been developed. Thus, a list of data from literature and field surveys have been gathered. After brain storming in experts panel and collecting data; data has been analyzed through Analytical Hierarchy Process utilizing the Expert Choice 11 software, which has resulted in seven major delay factors including: deficit budget allocation (27%), economic problems of the country (24%), the weakness of contractor's site management (13%), use of not qualified personnel in construction management (11%), delay in preparing and lots of mistakes/ modifications in detail design by the consultant (10%), inaccurate proposal in tenders by the contractor (8%), and improper selection of the contractor by the client (7%). The expert panel considers that the budget allocation is the most important cause of damage to project. Finally, damage causing factors have also been classified into six effective factors as project team, client, management consultancy, engineering consultant, contractor, and uncontrollable factors such as political, economic and social factors.
Singh, V.P., Dam Breach Modeling Technology, Kluwer, Dordrecht, Netherlands, 1996.
Baba, K., Hirose, T., Environmental Impact Assessment of Dams and Reserviors. Book chapter in Water Storage, Transport and Distribution, EOLSS Publications, 2009.
Thieme, M. L., Khrystenko, D., Qin, S., Kroner, R. E. G., Lehner, B., Pack, S., Tockner, K., Zarfl, C., Shahbol, N., Mascia, M. B. (2020). Dams and protected areas: Quantifying the spatial and temporal extent of global dam construction within protected areas. Conservation Letters, 13:e12719.
Wu, H., Chen, J., Xu, J., Zeng, G., Sang, L., Liu, Q., Yin, Z., Dai, J., Yin, D., Liang, J., Ye, S. (2019). Effects of dam construction on biodiversity: A review. Journal of Cleaner Production, 221: pp. 480-489.
Zare, R., Kalantari, B. (2018). Evaluating Negative Environmental Impacts Caused by Dam Construction. Urban Studies and Public Administration, 1:1: pp. 42-50.
Li, D., Lu, D., Moran, E., da Silva, R.F.B. (2020). Examining Water Area Changes Accompanying Dam Construction in the Madeira River in the Brazilian Amazon. Water, 12: 1921.
Chalekaee, A., Khodadad, M. (2016). Allocation of the client's and contractor's contribution in delays of construction projects with a Multi-Index Decision making Approach. Proceeding of the 2nd International Conference on Modern Research in Civil, Architecture and Urban Development, Istanbul, Turkey.
Heydarieh, S. A., Kheirandish, A. (2016). Investigating the Causes of Delay in Construction Projects and Determining Their Impact on the Cost, Time, and Quality Criteria. Proceeding of International Conference on Modern Management at Horizon of 1404, Tehran, Iran.
Yates, J. K. (1993). Construction Decision Support System for Delay Analysis. Journal of Construction Engineering and Management, Vol. 119, Issue 2: pp. 27-32.
Alamri, N., Amoudi, O., Njie, G. (2017). Analysis of Construction Delay Causes in Dams Projects in Oman. European Journal of Business and Social Sciences, 6: pp. 19-42.
Ahadi, H. R., Sepahi, A. (2013). Study and statistical analysis of the causes of delays in the implementation of Rail Construction Projects and presenting estimation model of economic loss by delays (DEI). 3rd international conference on recent advances in railway engineering, Tehran, Iran.
Kheyroddin, A., Asgari, M. (2014). Time Management and Identification of Runtime Optimization Factors in Construction Projects. 8th National Congress on Civil Engineering, Faculty of Civil Engineering, Babol, Iran.
Atafar, A., Eghbali, M. (2013). Pathology of Factors Affecting Delay in Projects in Region 3 of Iran's Gas Transmission Operations. Industrial Management Journal, Volume 5, Issue 2: pp. 85-102.
Babu, A. K. S., Meena, A. (2015). Study on time delay analysis for construction project delay analysis, Architecture department sathyabama university Chennai, India. International journal of engineering research and technology (IJERT), Vol. 4, Issue 03: ISSN: 2278-0181.
Aziz, R. F., Abdel-Hakam, A. A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria University Journal, Volume 55, Issue 2: pp. 1515-1539.
Larsen, J. K., Shen, G. Q., Lindhard, S. M., Brunou, T. D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32, 1: pp. 1-29.
Gebrehiwet, T., Luo, H. (2017). Analysis of delay impact on construction project based on RII and correlation coefficient: empirical study. Procedia Engineering, 196: pp. 366 – 374.
Marzouk, M. M., El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian construction Projects. Journal of Advanced Researched, Vol. 5, Issue 1: pp. 49-55.
Arditi, D., Nayak, S., Damci, A. (2017). Effect of organizational culture on delay in construction. International Journal of Project Management, 35: pp. 136–147.
Rahimian, A. H., Talebi, M., Zeynali, R. (2014). Execution Management Method of Project Delays. The first congress on construction management and evaluating projects, Gorgan, Iran.
Khoshand, A., Kamalan, H., Rezaei, H. (2018). Application of analytical hierarchy process (AHP) to assess options of energy recovery from municipal solid waste: a case study in Tehran, Iran. Journal of Material Cycles and Waste Management, Vol. 20(3): pp. 1689–1700.
Akhgari, P., Kamalan H. (2013). Economical–environmental evaluation of natural gas and renewable energy systems. International Journal of Energy Research, Vol. 37: pp. 1550–1561.
Kamalan, H., & Abedin Maghanaki, A. (2020). Root Cause Analysis of Delays in Dam Construction (Case Studies: Karun-3, Marun, Shafaroud and Jamishan Dams). Journal of Hydraulic Structures, 6(3), 45-58. doi: 10.22055/jhs.2020.35399.1148
MLA
Hamidreza Kamalan; Amir Abedin Maghanaki. "Root Cause Analysis of Delays in Dam Construction (Case Studies: Karun-3, Marun, Shafaroud and Jamishan Dams)", Journal of Hydraulic Structures, 6, 3, 2020, 45-58. doi: 10.22055/jhs.2020.35399.1148
HARVARD
Kamalan, H., Abedin Maghanaki, A. (2020). 'Root Cause Analysis of Delays in Dam Construction (Case Studies: Karun-3, Marun, Shafaroud and Jamishan Dams)', Journal of Hydraulic Structures, 6(3), pp. 45-58. doi: 10.22055/jhs.2020.35399.1148
VANCOUVER
Kamalan, H., Abedin Maghanaki, A. Root Cause Analysis of Delays in Dam Construction (Case Studies: Karun-3, Marun, Shafaroud and Jamishan Dams). Journal of Hydraulic Structures, 2020; 6(3): 45-58. doi: 10.22055/jhs.2020.35399.1148